Corewell Health - Health and Wellness Center Construction Timeline
The Corewell Health - Health and Wellness Center and Corewell Health Care Center are undergoing a major renovation project designed to enhance our facilities and better serve members, guests and patients.
Fri 8/7/26 - Fri 12/24/26 | 1st Floor Renovation
COMPLETED Demo Kitchen, Membership Sales Office,
Front Desk and Hydromassage Lounge
Mon 9/22/26 - Thurs 9/30/26 Wellness Corridor
Mon 9/28/26 - Thurs 10/13/26 Recovery Room (Infrared Sauna may not be available until Wednesday, October 14)
Thurs 11/2/26 - Wed 11/16/26 Sports Court - Closed for new flooring, court striping and wall paint (Reference Club App for class locations)
-
refer to Club App for Class Locations
Mon 11/16/26 - Mon 12/21/26 Men's and Women's Locker Rooms
Fri 11/27/26 - Thurs 12/24/26 Aquatic Area
Mon 10/27/26 - Tue 11/20/26 | 2nd Floor Renovation
Thurs 10/8/26 - Mon 10/19/26 Ride Studio
Wed 10/21/26 - Thurs 10/22/26 Studio A
Fri 10/10/26 - Fri 11/29/26 Fitness Floor - Executed in 3 Phases:
o Phase 1: 10/19-11/1 (pink)
o Phase 2: 11/2-11/15 (tan)
o Phase 3: 11/16-11/29 (purple)
-
Phase 1: 10/19-11/1 (pink)
-
Phase 2: 11/2-11/15 (tan)
-
Phase 3: 11/16-11/29 (purple)